‘Fast-track’ planning for housing schemes taking seven months

‘Fast-track’ planning for housing schemes taking seven months

New documents provided by An Bord Pleanála show that it is taking an average of around 30 weeks per large development, from the first consultation to the final decision

An Bord Pleanála’s ‘fast-track’ planning process for large housing developments is taking at least seven months on average.

It allows large developers to skip the normal planning process at council level in an attempt to speed up the delivery of estates and apartment blocks of over 100 units.

However, new documents provided by the board show that it is taking an average of around 30 weeks per large development, from the first consultation to...

Subscribe from just 1€

Exclusive offers

Choose the subscription that is right for you

Monthly Subscription

€1

For the first month

€19.99 Monthly Thereafter

Subscribe today

Cancel anytime

Annual Subscription

€200€149

For the first year

€199.99 annually thereafter

Subscribe today

Cancel anytime

Quarterly Subscription

€55€42

For the first 90 days

€55.00 quarterly Thereafter

Subscribe today

Cancel anytime

These offers are not available for current subscribers. Offers and pricing are subject to change without notice.

Terms & Conditions Apply

Please Subscribe or Log in to continue

Subscribe Login

Related Articles

More from The Business Post