A €2 million contractual fine will apply to Data and Power Hub Services Limited for their failure to deliver on their contractual terms. Picture: Getty

A gas power project contracted to start delivering electricity from next year has dropped out of the Irish market, leaving the country facing a growing power supply deficit.

The power project was due to be constructed by Data and Power Hub Services Limited, which is a partner company to Echelon data centres. It would have delivered 100MW of power to the electricity grid and was due to come online in south Dublin next year, but ...