State owes €5 million in fines over defunct Galway wind farm
Derrybrien facility has been taken offline by ESB after failed planning process
The state still owes more than €5 million in fines relating to the now-defunct Derrybrien wind farm in Galway following a ruling by the European Commission three years ago.
The wind farm, which was taken offline by the ESB earlier this year, has been subject to ongoing controversy after a peat landslide occurred in 2003 during its construction. In 2019, the Commission imposed fines on the state following an earlier ruling which found that Ireland ...