RPA holds back payment over Luas construction problems

The Railway Procurement Agency (RPA) is not yet ready to sign off on a 50-year warranty with the builders of the Luas - more than a year after the €775 million Dublin tram system opened.

6th August, 2005

A snag list involving a wide range of construction items will mean that the joint venture bui lder of the Luas, AMB, will not be paid its final multimillion euro instalment for some time.

According to sources, the builders had been considering whether to sue the RPA in recent weeks.

“We are doing lots of tests and doing a number of checks on various aspects of the system to make sure that we will get...

Subscribe from just €1 for the first month!

Exclusive offers:

All Digital Access + eReader

Trial

€1

Unlimited Access for 1 Month

Then €19.99 a month after the offer period.

Get basic
*New subscribers only
You can cancel any time.

Annual

€200

€149 For the 1st Year

Unlimited Access for 1 Year

You can cancel any time.

Quarterly

€55

€42

90 Day Pass

You can cancel any time.

2 Yearly

€315

€248

Unlimited Access for 2 Years

This product does not auto-renew

Team Pass

Get a Business Account for you and your team

Share this post

Related Stories

The best writing and and the biggest stories of 2019 from the Business Post

Richie Oakley | 7 months ago

Denis O’Brien is back in court, residents continue to fight the Council on halting site and a row surfaces in government over rent control proposals

Leanna Byrne | 4 years ago